Activity |
Date |
Status |
Develop Concept Design |
Dec 2020 |
Complete |
Club Member and User Group Consultation |
Jan 2021 |
Complete |
Pre-lodgement Meeting with Wollongong City Council |
Feb 2021 |
Complete |
Engage Consultants as per advice from Wollongong City Council |
Mar 2021 |
Complete |
Develop Detailed Design |
Aug 2021 |
Complete |
Received in-principal Landowners Consent from Wollongong City Council |
Aug 2021 |
Complete |
Receive Consultants Reports - Site Survey - Geotechnical Report - Bushfire Hazard Report - BCA (Building Code of Australia) Report - DDA (Disability Discrimination Act) Report - SEE (Statement of Environmental Effects |
Sep 2021 |
Complete |
Submission of DA Package to Wollongong City Council for Landowners Consent |
Dec 2022 |
90% |
WCC Landowners Consent |
Mar 2023 |
|
Submit DA and SEE |
Apr 2023 |
|
Develop Surf Club Facility Program Grant Application |
Jun 2023 |
|
Commence Fundraising Program |
Aug 2023 |
|
DA Approved |
Oct 2023 |
|
Submit Surf Club Facility Program Grant Application |
Oct 2023 |
|
Release Building Contract Tender |
Oct 2023 |
|
Surf Club Facility Program Grant Approved |
Feb 2024 |
|
Award Building Contract |
Mar 2024 |
|
Commence Construction (Surf Life Saving Off-season) |
Apr 2024 |
|
Completion of Surf Life Saving Elements and Building Access - Relocated Patrol Room / Observation Tower - Extension of Life Saving Equipment Storage - Lift and Stairwell - Accessible Ground Level Amenities |
Oct 2024 |
|
Practical Completion and Handover |
July 2025 |
|
Project Completion - Surf Club Facility Program Grant Acquittal |
Dec 2025 |