Activity

Date

Status

Develop Concept Design

Dec 2020

Complete

Club Member and User Group Consultation

Jan 2021

Complete

Pre-lodgement Meeting with Wollongong City Council

Feb 2021

Complete

Engage Consultants as per advice from Wollongong City Council

Mar 2021

Complete

Develop Detailed Design

Aug 2021

Complete

Received in-principal Landowners Consent from Wollongong City Council

Aug 2021

Complete

Receive Consultants Reports

-       Site Survey

-       Geotechnical Report

-       Bushfire Hazard Report

-       BCA (Building Code of Australia) Report

-       DDA (Disability Discrimination Act) Report

-       SEE (Statement of Environmental Effects

Sep 2021

Complete

Submission of DA Package to Wollongong City Council for Landowners Consent

Dec 2022

90%

WCC Landowners Consent

Mar 2023

 

Submit DA and SEE

Apr 2023

 

Develop Surf Club Facility Program Grant Application

Jun 2023

 

Commence Fundraising Program

Aug 2023

 

DA Approved

Oct 2023

 

Submit Surf Club Facility Program Grant Application

Oct 2023

 

Release Building Contract Tender

Oct 2023

 

Surf Club Facility Program Grant Approved

Feb 2024

 

Award Building Contract

Mar 2024

 

Commence Construction (Surf Life Saving Off-season)

Apr 2024

 

Completion of Surf Life Saving Elements and Building Access

-       Relocated Patrol Room / Observation Tower

-       Extension of Life Saving Equipment Storage

-       Lift and Stairwell

-       Accessible Ground Level Amenities

Oct 2024

 

Practical Completion and Handover

July 2025

 

Project Completion

-       Surf Club Facility Program Grant Acquittal

Dec 2025

 

2023/24 Season Statistics

Visitors To Stanwell Park Beach
Volunteer Patrol Hours
Volunteer Patrolling Life Savers
Preventative Actions
First Aid Cases
Rescues

2022/23 Season Statistics

Visitors To Stanwell Park Beach
Volunteer Patrol Hours
Volunteer Patrolling Life Savers
Preventative Actions
First Aid Cases
Rescues